PIPING FABRICATION PROCEDURE

 

PIPING FABRICATION

Pipe fabrication is the process of welding piping components such as pipes, elbows, tees, flanges, etc., into engineered piping systems in exact accordance with our customers' design requirements.


ACTIVE PIPING KNOWLEDGE 

  • 1.      Piping Materials
  • 2.      Dimensional Tolerance
  • 3.      Pipe Joints
  • 4.      But Welded and Socket welded piping.
  • 5.      Screw Piping
  • 6.      Flange connection
  • 7.      Branch Connection
  • 8.      Miter Bend and Fabricated Reducer
  • 9.      Cutting And Trimming of Standard Fittings & Pipe.
  • 10.   Galvanised Piping
  • 11.   Shop Fabrication.

1. Piping Materials:

·        All incoming materials shall be inspected as per approved ITP

·        Pipe, Pipe Fittings, Flange, Valve, Gasket, Stud Bolts etc all are check strictly as per PMS.

·        Materials Traceability shall be maintained for A.S, S.S, NACE, LTCS & transferring heat number.

·        Must be Colour Coadding for all piping materials as per procedure.

2.Dimensional Tolerance:

·        Dimension tolerance for piping fabrication shall be as per client standard. In order to adjust the variation in Dimension shown in AFC drawings & actual site, “Field Weld” shall be provided during fabrication.

·        Whenever error occur in drawings and bill of materials it shall be supervisor responsibility to notify the client.

 

3.Pipe Joints

·        Joining of line 2” and above in process and utility piping shall be pererered by butt weld.

·        Joining of line 1-1/2” and below shall be by socket welding/ Butt welding/ Threaded joints as specified in piping materials specification.

4. But Welded and Socket welded piping.

·        End preparation, Alignments and Fit-up of piece to be welded, Welding, Pre-heating and heat treatment (PWHT)shall be followed as describe in the welding specification chart.

·        NDT specification as along with tender documents

5.Screwed Piping

·        Galvanized Piping shall have thread as per ANSI B2.1.

·        Pipe thread shall be clean cut, without any burrs.

·        Threading of Pipe shall be done after bending or Heat treatment Operation.

·        During assembly of threaded joints, all threaded of pipe or fittings shall be cleaned.

·        The male threads shall be coated with thread sealant and the joint tightened sufficiently for leak proof joint.

6. Flange connection.

·        All Flange Facing shall be true and perpendicular to the Axis of the pipe to which they are attached.

·       Clean pipe flange, without forcing to bear uniform bolt tension and gasket compression & flange hole as per drawing.

·       Line item like orifice flanges, Spectacle blind, Strainer etc. shall be installed Following proper orientation.

·       A flange connection for the equipment’s shall be check for misassignment excessive gaps etc.

·       Extra care is to be exercised for flange connection to pump, turbines, cold boxes, air cooler.

·         Whenever a sceptical blind is to provided, Drilling and taping Jack screws in the flange shall be done before welding.

7. Branch connection: -

·        Branch connection with or without reinforcing pads shall be as indicates in the PMS.

·        For End preparation, Alignments, spacing, fit-up and welding and any of branch connection client guideline to be referred.

8. Cutting and Trimming of Standard fittings & pipe.

·        Component like pipe, elbow, Couplings, half couplings etc. shall be cut / trimmed edge preparation whenever required to meet fabrication and erection requirements as per drawings or as per client standard.

9. Shop Fabrication/ Prefabrication

·        The purpose of shop fabrication or pre-fabrication is to minimise work during the Erection.

·        Piping spool after fabrication stacked with proper identification marker on each spool.

·        During this period all flange raise face and threaded need to be extra care and to avoid physical damage also.

 

Welcome to Our Blog Active Piping Knowledge.

I am Afzal an experienced piping engineer from the last 8 years. Through this platform, I will share my experiences and knowledge with you in an innovative way. So be with me for the next couple of years!


For any Query  afzalpipingknowledge@gmail.com



 